You are here: Home / SOLUTION

How a Solar EPC Firm Reduced DC-Side Failures by 45% with SWM100 MCB

Views: 10     Author: Mark Zhang     Publish Time: 2026-08-06      Origin: 本站

Customer Background

A regional solar EPC contractor based in Southeast Asia manages 17 commercial and industrial rooftop PV installations ranging from 500 kW to 2.4 MW. The company also provides operations and maintenance (O&M) services for four third-party-owned solar plants. With more than 38,000 PV modules under management, the firm’s engineering team had long focused on inverter availability but began seeing a growing number of failures on the DC side — inside combiner boxes and string-level protection devices.

The company’s service contracts carried strict uptime guarantees. Every unplanned DC-side shutdown triggered penalty clauses and put renewal negotiations at risk. By early 2024, DC-related faults accounted for 60% of all site callouts. The operations director, who has 12 years in PV asset management, described the situation as “a silent reliability leak” that steadily eroded both margins and client trust.

Challenges and Pain Points

Most of the affected plants had been commissioned between 2018 and 2021 with AC-rated miniature circuit breakers used for DC string protection — a common shortcut in the region’s -growing solar market. Under normal load these breakers performed adequately, but during low-irradiance or partial-shading events, string volt-levels could rise beyond 600 V, and the breakers tripped without an actual fault. Whenever a real DC arc fault occurred, the breakers were slow to clear the fault, and in two incidents the contacts welded, allowing sustained fault amperage that damaged the combiner box and adjacent wiring.

After those incidents, the EPC firm switched to a low-cost DC MCB imported from a regional distributor. That solved the welding problem but introduced a new set of issues: nuisance tripping caused by thermal sensitivity under high ambient temperatures (above 40 °C) and a high rate of failure during insulation resistance testing. Over six months, the team replaced 23 failed breakers across their fleet. Replacement parts and travel labor added $14,000 to operating costs, while lost energy production from prolonged outages pushed the total financial impact past $32,000.

The core technical problem was clear: standard DC breakers did not have the arc-quenching performance or thermal derating characteristics needed for continuous outdoor operation in tropical climates. The company needed a device that could handle the DC arc dynamics and repeated switching operations without degrading.

Why SWM100 MCB?

The engineering team assessed three options in early 2024: upgrading to a higher-rated industrial DC breaker from a European brand, adding fuse-based string protection, or adopting the SINGI SWM100 MCB. The European solution offered strong performance but came at 2.5 times the unit cost and had a 14-week lead time — too slow for the company’s upcoming maintenance windows.

The SINGI SWM100 MCB stood out on three grounds. First, it is purpose-built for direct amperage applications up to 100 A per pole and rated for system volt-levels up to 1000 V DC, which matched the string configurations across the firm’s fleet. Second, its arc-extinguishing design uses a splitter-plate stack and optimized magnetic blow-out field, a configuration validated in arc simulation studies for DC MCBs. That engineering detail gave the team confidence in its fault-clearing ability—something the previous low-cost breakers lacked. Third, the SWM100 MCB meets both IEC 60947-2 and IEC 60898-2 standards, covering both industrial power distribution and PV installations.

Field testing also tipped the decision. The EPC firm installed eight SWM100 units in a 1.2 MW rooftop plant with known high heat exposure. After eight weeks of continuous monitoring, the breakers showed no nuisance trips, and contact resistance remained stable at less than 150 µΩ — a clear improvement over the regional product’s typical 280 µΩ reading after four weeks.

Implementation and Application Process

The rollout began in March 2024 and took 11 weeks. The project had four key stages:

  • Site audit and string mapping: For each plant, the team measured open-circuit volt-level, short-circuit current, cable lengths, and ambient temperature profiles at the combiner boxes. This data was used to choose the correct SWM100 pole configuration and trip curve.
  • Controlled replacement schedule: Replacements were timed to coincide with scheduled inverter maintenance to avoid additional downtime. On average, each combiner box took 45 minutes to update, including torque checks and insulation resistance verification.
  • Thermal derating validation: Six units were equipped with temporary thermocouples to compare internal temperature rise at rated load against datasheet derating curves. Measured temperatures were 9 °C below the upper limit specified for a 45 °C ambient environment.
  • Operator training: Local O&M crews received a half-day session on DC arc fault behavior and proper breaker choice, focusing on why AC breakers fail in DC circuits and how to read the SWM100’s trip status without exposing themselves to live parts.

The biggest challenge was retrofitting older combiner boxes that used non-standard DIN rail spacings. In two boxes, the existing busbar layout did not allow the SWM100 to be mounted without re-drilling. The team solved this by using a pre-fabricated adapter plate supplied by SINGI’s technical support, which added a day of lead time but avoided cutting any live busbars.

Application Results and Quantified Outcomes

Nine months after the first SWM100 MCB installation, the results are measurable across the entire fleet:

  • DC-side fault incidents fell by 45% — from an average of 14.2 events per quarter to 7.8 events.
  • Maintenance-related travel and spare-part costs dropped by 32%, saving roughly $21,000 in the first eight months after the upgrade.
  • Average fault-clearing time improved from 270 ms to less than 60 ms, based on waveform captures from two plants where string faults occurred during the assessment
  • Fleet availability rose from 98.6% to 99.4%, which allowed the EPC firm to meet its uptime guarantee for the fourth consecutive quarter and eliminated potential penalty costs of $8,400.

The secondary benefit was simpler root-cause analysis. With fewer nuisance trips and stable thermal performance, the maintenance team could confidently attribute alarms to real string-level issues (e.g., PID, damaged connector, or water intrusion) instead of questioning the protection device itself.

Customer Voice

“The SWM100 MCB is the first DC breaker that we installed and then forgot . Our technicians no longer carry spare breakers on every service call, and the thermal behaviour is consistent even at noon under full sun,” says the operations director. “We were skeptical of a new brand, but the arc-quenching performance and the IEC compliance documentation made the switch easy. The payback on the higher unit cost came in under five months.”

Lessons and Insights

Three takeaways from this project apply to any organization operating DC distribution systems:

  • Do not use AC-rated breakers for DC circuits. The physical arc interruption mechanism is different. As demonstrated by arc dynamics research, DC arcs have a sustained amperage that requires active arc splitting and magnetic blow-out, which only a purpose-designed DC MCB can provide.
  • Choose breakers based on real operating temperature, not catalogue ratings. Many low-cost DC breakers lack adequate thermal derating data, leading to nuisance trips in warm climates. Always request test curves or run a small pilot before fleet-wide deployment.
  • Build a breaker replacement schedule planned maintenance windows. Retrofitting protection devices during live operations introduces unnecessary risk. The team’s decision to combine the SWM100 upgrade with inverter maintenance reduced switching downtime by 60% compared to a standalone replacement program.

If the project were redone, the engineering team would insist on reviewing the breaker’s contact resistance measurements at 500 operations as part of the pilot. That data, now available from the first batch of SWM100 units, provides a useful baseline for predicting end-of-life behavior and scheduling proactive replacement.

References

SWM100 MCB

Singi Electrica is China manufacturer & supplier who mainly produces miniature circuit breaker, MCCB, SPD,distribution box , junction box with 24 years of experience. Hope to build business relationship with you.

Quick link

Product Center

Contact

Tel:0577 62053322
Phone:+86 18868286161
Email:salesmanager@singi.com
 
Copyright © 2023-2024 All Rights Reserved. 浙ICP备07016448号-2
💬